Construction of a toe drain at the north end of the East Dam at Copper Mountain Mine. Install and maintain a dam seepage diversion for the duration of construction (24/7 for 1 month). Excavate to embankment while design grades for drain construction. Haul and place backfill using various methods and material types in layers to the desired design limits.
Project Services and Scope
Excavation of trench to design elevation.
Backfill of trench to designed elevation with different types of aggregates in layers.
By-pass pumping and water management.
Managing all environmental plans and keeping in compliance with the environmental management plans set out by CMM.
Managing survey for this project including supply of as-builts.
Staying within all safety guidelines set out by CMM.
Supplying turnover packages during the course and after the work scope has been completed.
Supply trucks for the aggregate haul from to job site.