Bridge and Structural Works

Complexity Level 4 – Modular Bridge Design, Fabrication, and Installation

Lakeview Road post-wildfire hazard mitigation repairs

SERVICES AND SCOPE

  • Design, supply, fabrication, delivery, and installation of all new bridge substructure and superstructure components at 12 km Ashnola FSR.
  • Removal of existing bridge, excavation, and construction of new foundations.
  • Construction survey and layout, GRS wall installation, riprap placement, geotextile, approach barriers, and approach surfacing.
  • Completion of all testing requirements including NDT welding inspection, compaction testing, and grout sampling.
  • Work adjacent to and within the Ashnola River.
  •  

INDIGENOUS PARTICIPATION

Project completed with the participation and support of the Smelqmix (Similkameen) Nation through the Smelqmix Arrow Infrastructure Works Joint Venture

PROJECT VALUE

$2,500,000.00

PARTNER
BC Parks – Ministry of Environment and Parks

COMPLEXITY LEVEL 4
Advanced / High Complexity

PROJECT MANAGER
Garrett Blom
garrett.blom@arrow.ca
(250) 571-1940

PROJECT DATES
July – November 2025