Bridge and Structural Works
Complexity Level 4 – Modular Bridge Design, Fabrication, and Installation
Lakeview Road post-wildfire hazard mitigation repairs
SERVICES AND SCOPE
- Design, supply, fabrication, delivery, and installation of all new bridge substructure and superstructure components at 12 km Ashnola FSR.
- Removal of existing bridge, excavation, and construction of new foundations.
- Construction survey and layout, GRS wall installation, riprap placement, geotextile, approach barriers, and approach surfacing.
- Completion of all testing requirements including NDT welding inspection, compaction testing, and grout sampling.
- Work adjacent to and within the Ashnola River.
INDIGENOUS PARTICIPATION
Project completed with the participation and support of the Smelqmix (Similkameen) Nation through the Smelqmix Arrow Infrastructure Works Joint Venture
PROJECT VALUE
$2,500,000.00
PARTNER
BC Parks – Ministry of Environment and Parks
COMPLEXITY LEVEL 4
Advanced / High Complexity
PROJECT MANAGER
Garrett Blom
garrett.blom@arrow.ca
(250) 571-1940
PROJECT DATES
July – November 2025