Mine Infrastructure and Operations
Complexity Levels 3, 4 and 5 – Integrated Water, Reclamation, and Material Handling
Arrow Project Services delivered a comprehensive suite of civil construction services for Copper Mountain Mine, supporting the project with precision and reliability. Work included several projects including: constructing a collector trench and toe drain at the East Dam, managing 24/7 water diversions, executing detailed excavation and backfilling to design elevations, hauling and placing aggregate materials, 24/7 Load and Haul of oar feeding the mill, and overseeing environmental compliance, surveying, and quality control throughout the projects. These efforts were completed safely, professionally, and on schedule, reinforcing Arrow’s role as a trusted project partner.
Phase 1 of a dewatering system at the New Ingerbelle deposit. This system is to address immediate dewatering requirements at the New Ingerbelle pit. The focus is on the dewatering system is to integrate into the existing Fresh Water supply system, and operation strategy.
YEAR
April – November 2021
SERVICES AND SCOPE
- Earthworks and surface preparation of the dewatering system corridor
- Installation and assembly of dewatering pumps and pump skids
- Fusing and installation of 100-450mm HDPE mainline
- Bolt up and installation of 100mm-400mm carbon steel mainline
- Fabrication and assembly of various welded and flange connections to existing infrastructure
PROJECT VALUE
$500,000.00
Rebuilding approximately 710m length of the Wolf Creek Re-alignment channel. Establishing temporary water management of existing flows within the re-aligned channel to facilitate construction activities in the dry. Removing existing channel rip-rap and rip-rap transition fills in a method which enables re-use of the fills. Preparing of the channel foundation. Placing liner bedding fill, liner, rip-rap and rip rap transition fills. Re-establishing flow into the re-aligned channel.
YEAR
July 2021 – January 2022
SERVICES AND SCOPE
- Water By-pass a combination of gravity and pumped
- Foundation preparation for granular fill placement
- Liner bedding placement (lower and upper layer)
- Liner (Bituminous Geomembrane) Installation
PROJECT VALUE
$1,000,000.00
Rebuilding approximately 150m length of the Verdi/Wolf Creek channel and excavating the sediment trap to original design parameters. Establishing temporary water management of existing flows in the re-aligned canal to facilitate dry construction activities. Removing existing sediment and rip-rap transition fills in a method which enables re-use of the fills. Preparing of the channel foundation. Placing rip-rap and rip rap transition fills. Re-establishing flow into the re-aligned channel.
YEAR
September 2021 – January 2022
SERVICES AND SCOPE
- Install supplied 36” line upstream of stilling basin to direct storm event water around sediment trap (gravity fed)
- Construction and install a sump to direct Wolfe Creek water around sediment trap. Supply and install pump and piping to direct water around project (24-hour pump watch)
- Supply and install dewatering pump for sed pond and discharge line to direct water to pump house 50m from sed pond
- Remove existing silt curtains and reinstall
- Excavate 4,350m3 of sediments from the sediment trap material to be hauled 100m from project site
- Rehandle dewatered sediments to long term sediment storage 500m away
- Repair stilling basin. Remove rip-rap, remove sediments, replace rip-rap
PROJECT VALUE
$250,000.00
Re-building a 1,310m length of the WRSA Collection Ditch channel, including the removal and re-installation of an existing culvert, removal of two existing culverts and installation of a new culvert across the Mine Access Road to the WRSA Collection Ditch, and re-grading of the Mine Access Road to convey flow to the new culvert.
YEAR
October 2021 – May 2022
SERVICES AND SCOPE
- Establish temporary water management of existing flows within the channel to facilitate construction activities in the dry
- Remove existing channel rip-rap and rip-rap transition fills in a method that enables re-use of the fills
- Excavate the channel to the new design lines, which included re-sloping to 2H:1V. Additional clearing and grubbing
- Prepare channel foundation
- Re-establish elevation, minimum dimensions, and grade of the channel foundation
- Fill low spots with liner bedding
- Establish French Drains out of rip-rap transition fill and construct a revised liner tie in trench
- Place liner bedding, liner, rip-rap and rip rap transition fills
- Re-establish flow into the completed channel
- Excavate and remove existing culverts, place liner bedding and liner beneath culvert and re-install and backfill around new culvert
- Re-grade Copper Mountain Road and re-establish and re-grade Mine Access Road and ditch
PROJECT VALUE
$2,350,000.00
Construction of a collector trench at the base of the East Dam at Copper Mountain Mine. Install and maintain a creek diversion for the duration of construction (24/7 for 2 months). Excavate to embankment while design grades for trench construction. Haul and Place different material types to design grades to prepare for the bitumen liner installation. Backfill using various methods and material types in layers over the liner.
YEAR
May – August 2022
SERVICES AND SCOPE
- Excavation of trench to design elevation.
- Backfill of trench to designed elevation with different types of aggregates in layers.
- By-pass pumping and water management.
- Managing all environmental plans and keeping in compliance with the environmental management plans set out by CMM.
- Managing survey for this project including supply of as-builts.
- Staying within all safety guidelines set out by CMM.
- Supplying survey as-builds and turnover packages during the course and after the work scope has been completed.
- Supply trucks for the aggregate haul from security to job site.
- Provide daily reports and quality control documents for the engineer of record.
INDIGENOUS PARTICIPATION
Project completed with the full support and endorsement of Lower Similkameen Indian Band
PROJECT VALUE
$2,600,000.00
Construction of a toe drain at the north end of the East Dam at Copper Mountain Mine. Install and maintain a dam seepage diversion for the duration of construction (24/7 for 1 month). Excavate to embankment while design grades for drain construction. Haul and place backfill using various methods and material types in layers to the desired design limits.
YEAR
July – August 2022
SERVICES AND SCOPE
- Excavation of trench to design elevation.
- Backfill of trench to designed elevation with different types of aggregates in layers.
- By-pass pumping and water management.
- Managing all environmental plans and keeping in compliance with the environmental management plans set out by CMM.
- Managing survey for this project including supply of as-builts.
- Staying within all safety guidelines set out by CMM.
- Supplying turnover packages during the course and after the work scope has been completed.
- Supply trucks for the aggregate haul from to job site.
INDIGENOUS PARTICIPATION
Project completed with the full support and endorsement of Lower Similkameen Indian Band
PROJECT VALUE
$500,000.00
Construction of a toe drain at Copper Mountain Mine. Install and maintain a dam seepage diversion for the duration of construction (24/7 for 1 month). Excavate to embankment while design grades for drain construction. Haul and place backfill using various methods and material types in layers to the desired design limits.
YEAR
August – November 2023
SERVICES AND SCOPE
- Excavation of trench to design elevation.
- Backfill of trench to designed elevation with different types of aggregates in layers.
- By-pass pumping and water management.
- Managing all environmental plans and keeping in compliance with the environmental management plans set out by CMM.
- Managing survey for this project including supply of as-builts.
- Staying within all safety guidelines set out by CMM.
- Supplying turnover packages during the course and after the work scope has been completed.
INDIGENOUS PARTICIPATION
Project completed with the full support and endorsement of Lower Similkameen Indian Band
PROJECT VALUE
$1,300,000.00
YEAR
August – December 2024
SERVICES AND SCOPE
- Stripping of vegetation and excavation of unsuitable.
- Haul, place, and compact approximately 35,000m3 of cyclone sand.
- Managing all environmental plans and keeping in compliance with the environmental management plans set out by CMM.
- Managing survey for this project including supply of as-builts.
- Managing Quality Control.
- Staying within all safety guidelines set out by CMM.
- Supplying turnover packages during the course and after the work scope has been completed.
- Supply trucks for the aggregate haul from to job site.
INDIGENOUS PARTICIPATION
Project completed with the full support and endorsement of Lower Similkameen Indian Band
PROJECT VALUE
$1,000,000.00
YEAR
June 2025 – January 2026
SERVICES AND SCOPE
- Dozing and loading ore from the live stockpile to maintain a consistent 650 tph feed to the mill, ensuring uninterrupted mill operations.
- Loading and hauling SAG pebbles from the mill to the live pile at 100 tph using dedicated loaders, rock trucks, and support equipment.
- Supply of all major equipment including CAT 336 Excavators, CAT D8T Dozer, CAT 966 Loader, CAT 730 Rock Trucks, support crews, mechanics, and service vehicles for a continuous 24/7 operation with built-in redundancy.
- Operation of a fully self-contained loading and hauling program including fueling, DEF, lubricants, maintenance, communications, and equipment uptime management.
- Full redundancy in equipment and personnel (“hot changes”) to eliminate rushed or unsafe transitions.
- Environmental stewardship integrated into safety culture, including dust control, spill prevention, and proper handling of materials.
- The Work involves complex and safety-critical heavy equipment operations within an active mine site, requiring strict safety practices, disciplined communication, and a demonstrated safety-first mindset throughout the project.
INDIGENOUS PARTICIPATION
- Project delivered through the Smelqmix Arrow Infrastructure Works Joint Venture, supporting Indigenous economic development with the Lower Similkameen Indian Band
PROJECT VALUE
$10,000,000.00
Arrowhead partnered with Copper Mountain Mine Corporation and Arrow Transportation Systems Inc. to perform soil mixing and placement operations for the Mine’s ongoing progressive reclamation activities within the mine site. Arrowhead would receive feedstocks from Arrow Transportation and blend a reclamation soil that would then be hauled to completed areas of the mine and spread on the waste rock stockpiles. These efforts were performed in partnership with the Upper Similkameen Indian Band, with whom Arrowhead holds a benefit agreement with respect to all works performed at the mine site.
YEAR
June 2025 – January 2026
SERVICES AND SCOPE
- Dozing and loading ore from the live stockpile to maintain a consistent 650 tph feed to the mill, ensuring uninterrupted mill operations.
- Loading and hauling SAG pebbles from the mill to the live pile at 100 tph using dedicated loaders, rock trucks, and support equipment.
- Supply of all major equipment including CAT 336 Excavators, CAT D8T Dozer, CAT 966 Loader, CAT 730 Rock Trucks, support crews, mechanics, and service vehicles for a continuous 24/7 operation with built-in redundancy.
- Operation of a fully self-contained loading and hauling program including fueling, DEF, lubricants, maintenance, communications, and equipment uptime management.
- Full redundancy in equipment and personnel (“hot changes”) to eliminate rushed or unsafe transitions.
- Environmental stewardship integrated into safety culture, including dust control, spill prevention, and proper handling of materials.
- The Work involves complex and safety-critical heavy equipment operations within an active mine site, requiring strict safety practices, disciplined communication, and a demonstrated safety-first mindset throughout the project.
INDIGENOUS PARTICIPATION
Project delivered through the Smelqmix Arrow Infrastructure Works Joint Venture, supporting Indigenous economic development with the Lower Similkameen Indian Band
PROJECT VALUE
$10,00,000.00
Arrow Project Services provides a skilled workforce of heavy-equipment operators to support infrastructure construction and ongoing operations at Copper Mountain Mine. Personnel operate owner-supplied production equipment within an active mine environment, supporting the safe and efficient delivery of mine infrastructure work.
YEAR
September 2026 – 2028
SERVICES AND SCOPE
- Recruitment of experienced mine and heavy civil equipment operators
- Operation of large hydraulic shovels and excavators
- Operation of heavy production dozers
- Grader operation for haul-road construction and maintenance
- Workforce scheduling for rotating day and night shifts
- Personnel onboarding and coordination of Arrow and Copper Mountain Mine orientation requirements
- Continued personnel support to maintain appropriate operator coverage
PROJECT VALUE
$6,00,000.00
PARTNERS
Copper Mountain Mine
Hudbay Minerals
COMPLEXITY LEVEL 3
Intermediate / Complex
COMPLEXITY LEVEL 4
Advanced / High Complex
COMPLEXITY LEVEL 5
Critical / Program Level
PROJECT CONTACT
Brook Webster
bwebster@arrow.ca
(250) 571-6085
"Copper Mountain has partnered with Arrow Project Services (formerly Arrowhead) on a number of large construction projects throughout the past few years. Most recently Arrow Project Services was awarded and executed on an extension of our tailings management facility. The job was completed on time and on budget with the highest level of professionalism and a zero incident safety record. Arrow Project Services has always been honest and transparent and is considered to be an important business partner of Copper Mountain. We would look to hire Arrow Project Services in the future for construction projects of any scale."
Cory Forcier - Superintendent at Copper Mountain Mining Corp